Built Environment · CaaS dMRV
IPMVP Calculation Engine · Module 5

Auditable savings computation

The adjusted-baseline model is projected onto reporting-period conditions. Savings are accepted only when both Guideline 14 Table 5-2 thresholds and the IPMVP 2·SE significance test pass.

IPMVP Option BG14 hourly · CV(RMSE) ≤ 30% · |NMBE| ≤ 10%
Verified savings (this month)
8.0%
25.0 MWh
Annual verified savings
266.9 MWh
6.9% of baseline
2·SE threshold
276.0 MWh
Savings 0.97× threshold
Fractional savings uncertainty
51.7%
< 50% G14 cap @ 68% CI
Monthly savings

Adjusted baseline vs reporting

Statistical acceptance

Verdict

G14 · CV(RMSE) ≤ 30%12.4%PASS
G14 · |NMBE| ≤ 10%-2.1%PASS
G14 · annual uncertainty < 50% @ 68% CI51.7%FAIL
IPMVP · savings > 2·SE0.97×FAIL
Savings statistically significant: ✕ FAIL
Audit trace

Calculation walkthrough

Illustrative demo — synthetic reference data. Not live customer or production data.